Home MenuSouth Garner Greenway Extension
Photo Description: The above image shows a map with the project location circled.
Project Scope: This project includes design and installation of a 1.75-mile multi-use greenway path and 130-foot pedestrian bridge along Buffaloe Road, connecting the White Deer Park greenway to the Vandora Springs Drive roundabout. This multi-use path will connect several neighborhoods to nearby parks and events.
Funding Source: 2021 Parks and Recreational Bonds and LAPP Funding
Design Consultant: WithersRavenel
Current Status (updated November 2024): Design is 65% complete, this set will be used to start the NCDOT review process and utility coordination.
Project Schedule (tentative and subject to change):
Feasibility Study | Completed 2019 |
Feasibility Study Update | Completed 2022 |
Survey & Prelim Design | Completed Spring 2023 |
30% Design | Completed Summer 2023 |
Public Meeting | September 12, 2023 |
65% Design | Fall 2024 |
NCDOT/LAPP Review | Early 2025 |
Real Estate Acquisition (approx. 6 to 12 months) | Spring 2025 |
Preconstruction Coordination (Utility Coordination and Permitting) | Spring 2025 |
Final Design | Fall 2025 |
Construction Authorization (LAPP Requirement) | Spring 2026 |
Bidding | Summer 2026 |
Start of Construction | Late Summer 2026 |
Town Project Manager: Lisa Rodriguez
----------------------------------------------------------------------------------------------------