White Oak Current vs Future

Photo Description: The above image shows a side by side of the current conditions and future conditions. The current conditions of White Oak Road, Hebron Church Road, and Ackerman Road, which is currently a skewed T-intersection with a traffic signal. The image beside it shows future conditions which will be a partial dual-lane roundabout.

Project Scope: This project will include the installation of a partial dual-lane roundabout at the intersection of White Oak Road, Hebron Church Road, and Ackerman Road. The project will include street and storm drainage improvements, raised concrete splitter islands, private utility relocation/coordination, pavement markings and traffic signage.

Funding Source: LAPP Funding, 2013 and 2021 Street and Sidewalk Improvement Bonds

Design Consultant: Arcadis, Gresham Smith

Current Status (updated October 2024):  Utility relocations are progressing and anticipated to be complete Early 2025. The construction contract was awarded to Fred Smith Company and they will begin construction after utility relocations are complete. 

Project Schedule (tentative and subject to change):

Completed
Real Estate Acquisitions Completed
Final Permitting with NCDOT Completed
Utility Relocation In Progress
Bidding Completed
Start of Construction  Early 2025
End of Construction Late 2025

 

Town Project Manager: Lisa Rodriguez