06-20-23 Junction SE EC Matting_5

Photo Description: The above image shows the final conditions of the Junction Blvd Pipe outlet with matting and rip rap at the outlet.

Project Scope: This project is a continuation of the Town's efforts to repair aging and/or failing stormwater infrastructure in older municipal districts. The Junction Boulevard culvert was identified as a priority project for future bond funding in the Town's 2017 stormwater assessment. The project consists of a cured in place pipe liner to improve the integrity and longevity of the existing pipe. The pipe will be cleaned and inspected prior to installing the lining.

Funding Source: 2021 Stormwater Bonds

Design Consultant:  McAdams Co.

Current Status: Construction of this project was completed August 2023. 

Town Project Manager: Branyun Bullard