Town of Garner, NC
Home MenuForest Ridge Rd Storm Pipe Lining
Photo Description: The above image is a view of the upstream headwall of the completed project.
Project Scope: The Forest Ridge Road culvert project was identified as a priority for future bond funding in the 2017 stormwater assessment and will preserve the integrity of the stormwater conveyance as well as the street. The 60" arch corrugated metal pipe crossing Forest Ridge Road is in poor condition and will be lined to increase longevity. Additionally, repairs will be made to the headwalls, endwalls, and stream banks to stabilize the inlet and outlet.
Funding Source: 2021 Stormwater Bonds
Design Consultant: McAdams Co.
Town Project Manager: Branyun Bullard