Aversboro Sidewalks Map

Photo Description: The above image shows an aerial view of the project location.

Project Scope: This project includes sidewalk improvements along the west side of Aversboro Road (SR 2710) from the new YMCA complex to Berryfield Lane. Total project length is 0.17 miles. 

Funding Source: 2021 Street and Sidewalk Improvement Bonds

Design Consultant: TranSystems

Current Status (updated April 2024): Design is 100% complete, real estate acquisition will begin Spring 2024.

Project Schedule (tentative and subject to change):

100% Design Spring 2024
Public Meeting

 

September 21, 2023

Town Hall Training Room 900 7thAve. Garner, NC 27529
Final Design

 

Winter 2023

Preconstruction Coordination Summer 2024
Advertise Construction Bid                       Summer 2024

 

Town Project Manager: Branyun Bullard