Lake Drive Improvements Project

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Lake Drive improvements project

Work Scope: The Lake Drive improvements project will include a widening of the street with curb and gutter installed on both sides and sidewalk installed along the north side of the roadway

Begin Construction: Sept. 1, 2022

Projected End Construction: Spring 2023

Contractor: Daniels, Inc. of Garner and Narron Contracting

Engineer: Arcadis

For more information and future updates, please contact Town Project Manager Branyun Bullard at bbullard@garnernc.gov or at 984-233-2517.

Tap or click on the image below to view a PowerPoint presentation about the project that was shown at the Nov. 17 Town Council meeting.

Lake Drive improvements project


See a computer-generated 3D visualization of the proposed Lake Drive improvements.