Home MenuLake Drive Improvements Project
Work Scope: The Lake Drive improvements project will include a widening of the street with curb and gutter installed on both sides and sidewalk installed along the north side of the roadway
Begin Construction: Sept. 1, 2022
Projected End Construction: Spring 2023
Contractor: Daniels, Inc. of Garner and Narron Contracting
Engineer: Arcadis
For more information and future updates, please contact Town Project Manager Branyun Bullard at bbullard@garnernc.gov or at 984-233-2517.
Tap or click on the image below to view a PowerPoint presentation about the project that was shown at the Nov. 17 Town Council meeting.
See a computer-generated 3D visualization of the proposed Lake Drive improvements.